Kanchanpur, November 1, 2026 — Infrastructure built to irrigate 5,000 hectares of farmland under the third phase of the Mahakali Irrigation Project has been completed, but farmers cannot access water because India has yet to release supplies from the Tanakpur Barrage.
The 28-kilometre main canal, extending from Brahmadev to Phuleli in Shuklaphanta Municipality, was completed several years ago. Of the 22 branch canals planned to connect the main canal to farmland, 14 have been completed, while work on the remaining eight is nearing completion.